FY 2025 Major Projects
Projects in Planning
Central Campus Residential Development Phase 2 Housing Demolition
Lorch Hall Renovation and Addition
North Campus Research Complex Building 26 First Floor Labs and Office Renovation
Horace H. Rackham Educational Memorial 100 Farnsworth Street, Detroit Michigan
Raoul Wallenberg and Arthur Miller Houses Relocations and Renovations
Ross School of Business Lease at The Grand in Los Angeles, California
University of Michigan Health
- Grand Ledge Health Center Project
- Michigan Medicine Childcare Facility
- Troy Center for Specialty Care
University of Michigan Transportation Research Institute Addition
Projects in Progress
Flint College of Innovation & Technology Building | Work started March 2024 with an estimated completion date of March 2026. Financing is from a United States Department of Commerce Economic Development Administration grant, a Mott Foundation grant, gifts and U-M Flint.
Edward and Rosalie Ginsberg Building | Work started May 2023 with an estimated completion date of July 2025. Financing is from a gift.
Hadley Family Recreation & Well-Being Center | Work started December 2022 with an estimated completion date of December 2025. Financing is from reserves and Student Life.
Marsal Family School of Education at Marygrove Leasehold Improvements | Work started December 2023 with an estimated completion date of December 2025. Financing is from tenant improvement allowance and the Marsal Family School of Education.
Medical Science Unit I B and D Wings Renovation | Work started March 2023 with an estimated completion date of December 2025. Financing is from the Medical School.
New Building for the College of Pharmacy | Work started February 2023 with an estimated completion date of December 2025. Financing is from reserves and gifts.
New Central Campus Residential Development | Work started September 2023 with an estimated completion date of September 2026. Financing is from reserves and Housing.
New Michigan Marching Band Practice Field | Work started February 2023 with an estimated completion date of September 2026. Financing is from reserves.
Nichols Drive Slope Stabilization | Work started October 2024 with an estimated completion date of March 2026. Financing is from reserves.
Observatory Hall Reserve Officers Training Corps Space Renovation | Work started March 2024 with an estimated completion date of September 2025. Financing is from reserves and the Office of the Provost.
On Campus Solar Installation | Work started May 2025 with an estimated completion date of May 2028. Financing is from the general fund, bond proceeds, and recovery through internal utility rates.
Ross School of Business Executive Dormitory and Sam Wyly Hall Renovations | Work started January 2025 with an estimated completion date of December 2026. Financing is from the Stephen M. Ross School of Business.
U-M Center for Innovation | Work started December 2023 with an estimated completion date of September 2027. Financing is from a gift, a state grant and development activities.
University of Michigan Health | Financing is from University of Michigan Health.
- Clinical Expansion Project 300 W. Michigan Avenue, Ypsilanti, Michigan | Work started January 2023 with an estimated completion date of August 2025. Financing is from tenant improvement allowance and University of Michigan Health.
- D. Dan and Betty Kahn Health Care Pavilion | Work restarted May 2021 with an estimated completion date of November 2025.
- Rogel Cancer Center Infrastructure Upgrades | Work started June 2024 with an estimated completion date of March 2026.
Zina Pitcher Parking Structure | Work started December 2024 with an estimated completion date of March 2026. Financing is from University of Michigan Health and Logistics, Transportation & Parking.
Projects Completed
William Davidson Player Development Center Renovate and Expand Team Areas | Completed October 2024. Financed by Athletic department gifts.
Dearborn Renick University Center First Floor Renovations | Completed December 2024. Financed by U-M Dearborn.
Electric Vehicle Center Battery Laboratory Expansion | Completed March 2025. Financed by the College of Engineering.
Hayward Street Geothermal Facility | Completed October 2024. Financed by reserves.
Leinweber Computer Science and Information Building | Completed February 2025. Financed by state capital appropriation, the Office of the Provost, the College of Engineering, and the School of Information.
Glenn E. Schembechler Hall Renovate Team Locker Room | Completed July 2024. Financed by Athletic department gifts.
School of Nursing Building 1 Classroom and Interior Renovation | Completed March 2025. Financed by the School of Nursing.
University of Michigan Health | Financed by University of Michigan Health.
- C.S. Mott Children’s and Von Voigtlander Women’s Hospitals New Children’s Emergency Services Fast Track Clinic | Completed April 2025.
- A. Alfred Taubman Health Care Center Air Handling Unit Replacement | Completed June 2025.
- A. Alfred Taubman Health Care Center Fire Alarm Replacement | Completed January 2025.
- University Hospital Electrical Substation Replacement | Completed November 2025.
- University Hospital South Renovation | Completed April 2025.